The following procedure shall be used to load the necessary software to the workstation and provide designs to the test fixture. The intent of these test steps are to ensure the workstation is set up appropriately and the test fixture design is captured.
Install the ADIM-Flasher tool onto your workstation.
Go through the setup wizard to successfully install it.
Install the Studio Interface Kit onto your workstation.
Go through the setup wizard to successfully install it.
The following procedure will go through the design of the test fixture that is necessary to execute the manufacturing tests for EVIC.
Use x5 22k resistors in series, powered from 5V to generate different voltages for each channel. See schematic below for wiring connector pins P4 and P5.
Use x7 inverters on pins 1-7 on connector P3. The inverters are used to convert ground to 12V. No inverter is needed for pin 8. See schematic below for wiring connector pins P3 and P5.
A test EVIC board is needed to transmit CAN messages onto the CAN lines of a production EVIC board. Each CAN line (High and Low) will need to be wired to both the Test and Production EVIC boards.