The following instructions procedure shall be used to set-up the text fixture, load the necessary kernel and test software to validate the results. The intent of these test steps are to ensure the quality of EVIC EVIC’s production boards.
...
Sections
· Analog Inputs (5)
· Digital Outputs (8)
· Digital Inputs (8)
· CAN (1 channel)Kernel Loading Procedure
· Software Verifier Procedure
· Test Setup Fixture
· Results
Analog Inputs
Use x5 22k resistors in series, powered from 5V to generate different voltages for each channel. See schematic below for wiring connector pins P4 and P5.
...